Scheme Details
DISTRICT
Basti
AGENCY
Megha
SCHEME ID
20074482
SCHEME NAME
DEVERA GANJ BARAR GP wss
ESTIMATED COST
139.92
EXPENDITURE
84.66
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
13
Procured
13
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
2237.00
Meter
Length Laid
2237.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Dubaulia | Devara Ganj Barar | 450433 | Bhatiha | 14 | 14 | 100% | Har Ghar Jal | Not Certified |
| 2 | Basti | Dubaulia | Devara Ganj Barar | 450434 | Para | 76 | 76 | 100% | Har Ghar Jal | Not Certified |
| 3 | Basti | Dubaulia | Devara Ganj Barar | 450435 | Dasharathpur | 8 | 8 | 100% | Har Ghar Jal | Not Certified |
| 4 | Basti | Dubaulia | Devara Ganj Barar | 680632 | Matiha | 14 | 14 | 100% | Har Ghar Jal | Not Certified |
| 5 | Basti | Dubaulia | Devara Ganj Barar | 693759 | DEWARA GANGWARAR | 170 | 170 | 100% | Har Ghar Jal | Not Certified |