Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20074546 | SONAURA GP wss | 173.79 | 79.63 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 17 | 17 | Yes | 0 | NA | No | 8996.00 | 10721.60 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Sau Ghat | Sonura | 450801 | Badarjoot | 64 | 64 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Sau Ghat | Sonura | 450802 | Mahroopur | 38 | 38 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Sau Ghat | Sonura | 450803 | Sonaura | 171 | 171 | 100 | Har Gar Jal | Not Certified |