Scheme Details
DISTRICT Basti
AGENCY Megha
SCHEME ID 20074607
SCHEME NAME PAKARI CHAUHAN GP wss
ESTIMATED COST 203.02
EXPENDITURE 113.04
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 5
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 17
Procured 17 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10798.00 Meter
Length Laid 10798.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

5 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Basti Dubaulia Pakari Chauhan 450224 Pakari Chauhan 211 211 100% Har Ghar Jal Not Certified
2 Basti Dubaulia Pakari Chauhan 450225 Mirzapur 25 25 100% Har Ghar Jal Not Certified
3 Basti Dubaulia Pakari Chauhan 450226 Kalyanpur 6 6 100% Har Ghar Jal Not Certified
4 Basti Dubaulia Pakari Chauhan 450227 Sisauni 129 128 99% Work In Progress Not Certified
5 Basti Dubaulia Pakari Chauhan 450228 Rampur 1 1 100% Har Ghar Jal Not Certified