Scheme Details
DISTRICT
Basti
AGENCY
Megha
SCHEME ID
20074609
SCHEME NAME
SAUR BARWA & MUDSARA GP wss
ESTIMATED COST
267.15
EXPENDITURE
117.31
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
24
Procured
24
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11689.00
Meter
Length Laid
7606.80
Meter
Scheme Assigned Villages
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Gaur | Mudsara | 449455 | Mudsara | 276 | 275 | 100% | Work In Progress | Not Certified |
| 2 | Basti | Gaur | Suar Barwa | 449456 | Gorshara | 77 | 76 | 99% | Work In Progress | Not Certified |
| 3 | Basti | Gaur | Mudsara | 449457 | Mashjidiya | 75 | 74 | 99% | Work In Progress | Not Certified |
| 4 | Basti | Gaur | Suar Barwa | 449458 | Chikani | 43 | 43 | 100% | Har Ghar Jal | Not Certified |
| 5 | Basti | Gaur | Suar Barwa | 449459 | Suar Barwa | 103 | 102 | 99% | Work In Progress | Not Certified |