DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20075117
SCHEME NAME Daud Pur Water Supply Scheme
ESTIMATED COST 286.83
EXPENDITURE 184.92
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 6
Procured 6 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11151.00 Meter
Length Laid 9692.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Banki Daud Pur 435223 Daud Pur 269 267 99% Work In Progress Not Certified
2 Barabanki Banki Daud Pur 435224 Sahelia 135 133 99% Work In Progress Not Certified