Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Dara- Eco Protection (JV) | 20075272 | Jaitapur naubasta kalan water supply | 389.51 | 56.18 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 27 | Yes | 0 | NA | No | 16127.00 | 16000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Gasari | Naubasta Kalan | 443990 | Naubasta Kalan | 169 | 164 | 97 | Work In Progress | Not Certified |
| 2 | Balrampur | Gasari | Jaitapur | 444012 | Jaitapur | 264 | 249 | 94 | Work In Progress | Not Certified |