Scheme Details
DISTRICT
Bahraich
AGENCY
PNC-SPML-JV
SCHEME ID
20075318
SCHEME NAME
CHAHLAR JARWAL MVS PWS
ESTIMATED COST
166.48
EXPENDITURE
96.96
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
25
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10181.00
Meter
Length Laid
10481.00
Meter
Scheme Assigned Villages
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bahraich | Jarwal | Chahlar | 442803 | Dihawa Khurd | 48 | 45 | 94% | Work In Progress | Not Certified |
| 2 | Bahraich | Jarwal | Chahlar | 442808 | Chahlar | 115 | 113 | 98% | Work In Progress | Not Certified |