Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20075363
SCHEME NAME Riwan Chappri & Nandankala Water Supply Scheme
ESTIMATED COST 362.39
EXPENDITURE 247.48
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 7
Procured 7 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 13339.00 Meter
Length Laid 13250.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Fatehpur Riwan Chapri 434585 Riwan 291 290 100% Work In Progress Not Certified
2 Barabanki Fatehpur Nandanakala 434609 Nandanakala 174 172 99% Work In Progress Not Certified
3 Barabanki Fatehpur Nandanakala 434610 Sainbasi 82 80 98% Work In Progress Not Certified