Scheme Details
DISTRICT
Ghazipur
AGENCY
HFCL- JWIL (JV)
SCHEME ID
20075396
SCHEME NAME
MAKHANPUR W/S SCHEME (HFCL)
ESTIMATED COST
174.41
EXPENDITURE
82.42
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9877.00
Meter
Length Laid
6754.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Jakhania | Makhanpur | 471573 | Makhanpur | 118 | 115 | 97% | Work In Progress | Not Certified |
| 2 | Ghazipur | Jakhania | Makhanpur | 471574 | Lulapur | 23 | 22 | 96% | Work In Progress | Not Certified |
| 3 | Ghazipur | Jakhania | Makhanpur | 471575 | Jagdish Gurudatta | 86 | 82 | 95% | Work In Progress | Not Certified |