Scheme Details
DISTRICT
Basti
AGENCY
VSA
SCHEME ID
20075419
SCHEME NAME
DHARAM NAGAR & HARI GAON GP wss
ESTIMATED COST
451.64
EXPENDITURE
334.71
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
28010.00
Meter
Length Laid
23100.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Paras Rampur | Hari Gaon | 449100 | Hari Gaon | 418 | 417 | 100% | Work In Progress | Not Certified |
| 2 | Basti | Paras Rampur | Dharm Nagar | 449150 | Dharam Nagar | 109 | 108 | 99% | Work In Progress | Not Certified |
| 3 | Basti | Paras Rampur | Dharm Nagar | 449151 | Pipari Pokhar | 39 | 30 | 77% | Work In Progress | Not Certified |
| 4 | Basti | Paras Rampur | Dharm Nagar | 449152 | Bhojpur | 50 | 34 | 68% | Work In Progress | Not Certified |
| 5 | Basti | Paras Rampur | Dharm Nagar | 449153 | Sekhui | 30 | 21 | 70% | Work In Progress | Not Certified |