Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | NCC Ltd. | 20075428 | Kapasi & Ballipur JJM SCHEME | 457.45 | 274.90 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 32255.00 | 24612.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Lakhimpur Kheri | Mitoli | Kapasi | 408663 | Kapasi | 380 | 380 | 100 | Har Gar Jal | Certified | 
| 2 | Lakhimpur Kheri | Mitoli | Ballipur | 408672 | Ballipur | 87 | 87 | 100 | Har Gar Jal | Not Certified | 
| 3 | Lakhimpur Kheri | Mitoli | Ballipur | 408673 | Chhattapur | 87 | 87 | 100 | Har Gar Jal | Not Certified | 
| 4 | Lakhimpur Kheri | Mitoli | Ballipur | 408674 | Katkherwa | 32 | 32 | 100 | Har Gar Jal | Not Certified | 
| 5 | Lakhimpur Kheri | Mitoli | Ballipur | 408675 | Bardha | 62 | 62 | 100 | Har Gar Jal | Not Certified | 
| 6 | Lakhimpur Kheri | Mitoli | Ballipur | 408676 | Badhaiya | 19 | 19 | 100 | Har Gar Jal | Not Certified | 
| 7 | Lakhimpur Kheri | Mitoli | Ballipur | 408677 | Behdamoti | 7 | 7 | 100 | Har Gar Jal | Not Certified |