Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Dara- Eco Protection (JV) | 20075442 | Baluwa Balui Water Supply | 420.16 | 188.16 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 16787.00 | 16711.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Balrampur | Balrampur | Baluwa Balui | 443729 | Baluwa Balui | 673 | 655 | 97 | Work In Progress | Not Certified | 
| 2 | Balrampur | Balrampur | Baluwa Balui | 443730 | Saddopur | 84 | 67 | 80 | Work In Progress | Not Certified |