Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | M/s Sudhakara Infratech Pvt. Ltd | 20075471 | BHILAULI KHALSA WATER SUPPLY SCHEME | 325.60 | 110.63 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 7 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 23 | 23 | NA | 0 | NA | No | 13664.00 | 9518.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462558 | Bhilauli Khalsa | 136 | 132 | 97 | Work In Progress | Not Certified | 
| 2 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462559 | BHILAULI AIMA | 58 | 46 | 79 | Work In Progress | Not Certified | 
| 3 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462560 | Chzck Jalal | 15 | 12 | 80 | Work In Progress | Not Certified | 
| 4 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462561 | Motideh | 3 | 1 | 33 | Work In Progress | Not Certified | 
| 5 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462562 | Chack Mazmu | 111 | 107 | 96 | Work In Progress | Not Certified | 
| 6 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462563 | GOKULPUR AIMA | 18 | 14 | 78 | Work In Progress | Not Certified | 
| 7 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462564 | Ramani Pur | 113 | 106 | 94 | Work In Progress | Not Certified |