Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20075471
SCHEME NAME
BHILAULI KHALSA WATER SUPPLY SCHEME
ESTIMATED COST
325.60
EXPENDITURE
233.56
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
13664.00
Meter
Length Laid
9518.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
8 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462558 | Bhilauli Khalsa | 136 | 132 | 97% | Work In Progress | Not Certified |
| 2 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462559 | BHILAULI AIMA | 58 | 58 | 100% | Har Ghar Jal | Not Certified |
| 3 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462560 | Chzck Jalal | 15 | 12 | 80% | Work In Progress | Not Certified |
| 4 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462561 | Motideh | 3 | 1 | 33% | Work In Progress | Not Certified |
| 5 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462562 | Chack Mazmu | 111 | 107 | 96% | Work In Progress | Not Certified |
| 6 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462563 | GOKULPUR AIMA | 18 | 14 | 78% | Work In Progress | Not Certified |
| 7 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 462564 | Ramani Pur | 113 | 106 | 94% | Work In Progress | Not Certified |
| 8 | Azamgarh | Tahbarpur | Bhilauli Khalsa | 680457 | Gokulpur Khalsa | 6 | 1 | 17% | Work In Progress | Not Certified |