Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20075500
SCHEME NAME
KARIYABAR WATER SUPPLY SCHEME
ESTIMATED COST
242.70
EXPENDITURE
130.95
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10053.00
Meter
Length Laid
8700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Tahbarpur | Kariyabar | 462600 | Kariyabar | 273 | 259 | 95% | Work In Progress | Not Certified |
| 2 | Azamgarh | Tahbarpur | Kariyabar | 462601 | Chuk Jorawar | 10 | 10 | 100% | Har Ghar Jal | Not Certified |