DISTRICT Siddharth Nagar
AGENCY VSA
SCHEME ID 20075510
SCHEME NAME UDAIPUR AND BHARTHANA GP WSS
ESTIMATED COST 381.15
EXPENDITURE 150.05
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 6
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15253.00 Meter
Length Laid 15545.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

6 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Siddharth Nagar Mithwal Bharthana 447323 Bhrthna 165 151 92% Work In Progress Not Certified
2 Siddharth Nagar Mithwal Bharthana 447324 Susauli 30 24 80% Work In Progress Not Certified
3 Siddharth Nagar Mithwal Bharthana 447325 Chimti 4 4 100% Har Ghar Jal Not Certified
4 Siddharth Nagar Mithwal Udaipur 447327 Udaipur 145 138 95% Work In Progress Not Certified
5 Siddharth Nagar Mithwal Udaipur 447328 Gorwa Pakar 49 47 96% Work In Progress Not Certified
6 Siddharth Nagar Mithwal Udaipur 447329 Gopalpur 36 34 94% Work In Progress Not Certified