Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | VSA | 20075511 | AMOULI & DHOHVA PANDAY GP wss | 302.29 | 206.27 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 20 | 20 | Yes | 0 | NA | No | 15676.00 | 15676.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Paras Rampur | Amouli | 449158 | Amouli | 146 | 146 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Paras Rampur | Dhohva Panday | 449165 | Dhohva Panday | 116 | 115 | 99 | Work In Progress | Not Certified |
| 3 | Basti | Paras Rampur | Dhohva Panday | 449166 | Sebra Patti Nathpur | 30 | 30 | 100 | Har Gar Jal | Not Certified |
| 4 | Basti | Paras Rampur | Dhohva Panday | 449167 | Bichhauliya | 57 | 56 | 98 | Work In Progress | Not Certified |
| 5 | Basti | Paras Rampur | Dhohva Panday | 449168 | Bandri | 40 | 39 | 98 | Work In Progress | Not Certified |