Scheme Details
DISTRICT
Kaushambi
AGENCY
GA INFRA - BABA (JV)
SCHEME ID
20075545
SCHEME NAME
Bairampur - Kolhuwa Water Supply Scheme
ESTIMATED COST
315.59
EXPENDITURE
149.82
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12603.00
Meter
Length Laid
12603.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kaushambi | Sarsawan | KOLHUWA | 431130 | KOLHUWA | 324 | 301 | 93% | Work In Progress | Not Certified |
| 2 | Kaushambi | Sarsawan | Bairampur` | 431176 | Bairampur | 220 | 200 | 91% | Work In Progress | Not Certified |
| 3 | Kaushambi | Sarsawan | NEGREHA KALA | 431177 | Negereha Khurd | 58 | 58 | 100% | Har Ghar Jal | Certified |