Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Aligarh | PNC-SPML-JV | 20075549 | BARAKALAN & NARRAU WSS | 437.71 | 119.31 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 23823.00 | 23000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Aligarh | Akrabad | Golara | 395185 | Nagla Lala | 83 | 78 | 94 | Work In Progress | Not Certified | 
| 2 | Aligarh | Akrabad | Bara Kalan | 395198 | Bara Kalan | 158 | 154 | 97 | Work In Progress | Not Certified | 
| 3 | Aligarh | Akrabad | Bara Kalan | 395199 | Thiramai | 132 | 105 | 80 | Work In Progress | Not Certified | 
| 4 | Aligarh | Akrabad | Narrau | 395200 | Narrau | 284 | 275 | 97 | Work In Progress | Not Certified |