Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20076171 | AAMA 3rd BANSAPAR GP wss | 299.95 | 97.81 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 14085.00 | 13873.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Saltaua Gopal Pur | Bansapar | 448981 | Tahauwa | 4 | 4 | 100 | Har Gar Jal | Not Certified |
| 2 | Basti | Saltaua Gopal Pur | Bansapar | 448982 | Dadaya Khurd | 1 | 1 | 100 | Har Gar Jal | Not Certified |
| 3 | Basti | Saltaua Gopal Pur | Bansapar | 449024 | Bansapar | 229 | 229 | 100 | Har Gar Jal | Not Certified |
| 4 | Basti | Saltaua Gopal Pur | Bansapar | 449025 | Rehar Babu | 40 | 38 | 95 | Work In Progress | Not Certified |
| 5 | Basti | Saltaua Gopal Pur | AAMA 3rd | 449063 | Narayanpur | 146 | 145 | 99 | Work In Progress | Not Certified |
| 6 | Basti | Saltaua Gopal Pur | AAMA 3rd | 680606 | Narainpur | 330 | 330 | 100 | Har Gar Jal | Not Certified |