Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20076174
SCHEME NAME Dhakia Khairuddun Water Supply
ESTIMATED COST 203.90
EXPENDITURE 110.71
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 16
Procured 16 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 6078.00 Meter
Length Laid 5910.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Nawabganj DHAKIA KHAIRUDDIN 403810 DHAKIA KHAIRUDDIN 192 192 100% Har Ghar Jal Not Certified
2 Bareilly Nawabganj DHAKIA KHAIRUDDIN 403811 BASENGA 230 230 100% Har Ghar Jal Not Certified