Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Basti
AGENCY Megha
SCHEME ID 20076189
SCHEME NAME MUNIAWN GP wss
ESTIMATED COST 162.97
EXPENDITURE 67.40
AUTOMATION STATUS
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 13
Procured 13 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 5452.00 Meter
Length Laid 10561.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Basti Saltaua Gopal Pur Muniawn 448912 Muniawn 174 174 100% Har Ghar Jal Not Certified
2 Basti Saltaua Gopal Pur Muniawn 448913 Manikaura 105 75 71% Work In Progress Not Certified