Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | GVPR | 20076280 | Kanjhiyana mvs | 375.97 | 167.46 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 28 | 28 | Yes | 0 | NA | No | 12015.00 | 12015.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Kamalganj | Kanjhiyana | 418652 | Kanjhiyana | 282 | 282 | 100 | Har Gar Jal | Not Certified | 
| 2 | Farrukhabad | Kamalganj | Jhijhuki | 418653 | Jhijhuki | 141 | 109 | 77 | Work In Progress | Not Certified | 
| 3 | Farrukhabad | Kamalganj | Niyamatpur Thakuran | 418655 | Niyamatpur Thakuran | 214 | 76 | 36 | Work In Progress | Not Certified | 
| 4 | Farrukhabad | Kamalganj | Jhijhuki | 656120 | BARUA KHEDA | 40 | 40 | 100 | Har Gar Jal | Not Certified |