Scheme Details
DISTRICT
Barabanki
AGENCY
PNC-SPML-JV
SCHEME ID
20076374
SCHEME NAME
Piprauli Water Supply Scheme
ESTIMATED COST
287.46
EXPENDITURE
169.34
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11406.00
Meter
Length Laid
9712.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Nindaura | Piprauli | 434458 | Piprauli | 675 | 669 | 99% | Work In Progress | Not Certified |