Scheme Details
DISTRICT
Farrukhabad
AGENCY
GVPR
SCHEME ID
20076407
SCHEME NAME
Khagau w/s scheme
ESTIMATED COST
504.57
EXPENDITURE
348.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18644.00
Meter
Length Laid
18076.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Shamsabad | Naglakalar | 418276 | Naglakalar | 189 | 173 | 92% | Work In Progress | Not Certified |
| 2 | Farrukhabad | Shamsabad | Baghau | 418277 | Baghau | 168 | 163 | 97% | Work In Progress | Not Certified |
| 3 | Farrukhabad | Shamsabad | Baksuri | 418278 | Baksuri | 165 | 165 | 100% | Har Ghar Jal | Not Certified |
| 4 | Farrukhabad | Shamsabad | Khagau | 418279 | Khagau | 220 | 220 | 100% | Har Ghar Jal | Not Certified |
| 5 | Farrukhabad | Shamsabad | Baksuri | 657338 | GUJARPUR | 45 | 19 | 42% | Work In Progress | Not Certified |