Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | GVPR | 20076469 | Gusrapur w/s scheme | 655.38 | 390.28 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 42 | 42 | Yes | 0 | NA | No | 26035.00 | 24591.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Farrukhabad | Shamsabad | Kandhemai | 418284 | Kandhemai | 210 | 169 | 80 | Work In Progress | Not Certified |
| 2 | Farrukhabad | Shamsabad | Gusrapur | 418285 | Gusrapur | 289 | 289 | 100 | Har Gar Jal | Not Certified |
| 3 | Farrukhabad | Shamsabad | Baghauna | 418288 | Baghauna | 533 | 461 | 86 | Work In Progress | Not Certified |
| 4 | Farrukhabad | Shamsabad | Kandhemai | 657503 | DUDHIYAPUR | 30 | 30 | 100 | Har Gar Jal | Not Certified |