Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Chandauli | GA INFRA - BABA (JV) | 20076497 | HUSEPUR_CHAKIYA BIHARI MISHRA WS | 345.43 | 261.29 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 23 | 23 | Yes | 0 | NA | No | 21299.00 | 21286.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Chandauli | Chahaniya | Chakiya Bihari Mishra | 474104 | Chakiya Bihari Mishra | 121 | 121 | 100 | Har Gar Jal | Not Certified | 
| 2 | Chandauli | Chahaniya | Husepur | 474105 | Husepur | 127 | 127 | 100 | Har Gar Jal | Not Certified | 
| 3 | Chandauli | Chahaniya | Chakiya Bihari Mishra | 474106 | Jairampur | 126 | 126 | 100 | Har Gar Jal | Not Certified | 
| 4 | Chandauli | Chahaniya | Husepur | 474108 | Sherpur | 151 | 151 | 100 | Har Gar Jal | Not Certified |