Scheme Details
DISTRICT
Muzaffarnagar
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20076933
SCHEME NAME
PUTTHI IBRAHIMPUR MV WSS
ESTIMATED COST
398.26
EXPENDITURE
194.89
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11788.00
Meter
Length Laid
11699.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Muzaffarnagar | Jansath | Putthi Ibrahimpur | 385423 | Tikaula | 149 | 93 | 62% | Work In Progress | Not Certified |
| 2 | Muzaffarnagar | Jansath | Putthi Ibrahimpur | 385424 | Putthi Ibrahimpur | 778 | 748 | 96% | Work In Progress | Not Certified |