Scheme Details
DISTRICT
Baghpat
AGENCY
LC INFRA
SCHEME ID
20077060
SCHEME NAME
JIWANA RO W/S SCHEME
ESTIMATED COST
199.22
EXPENDITURE
86.80
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
10
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8436.00
Meter
Length Laid
8265.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Baghpat | Baraut | Jiwana | 391939 | Jiwana | 490 | 475 | 97% | Work In Progress | Not Certified |