Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | PNC-SPML-JV | 20077065 | Gokulpur & Aseni Water SUpply Scheme | 417.48 | 111.89 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | No | 0 | NA | No | 19599.00 | 17737.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Banki | Aseni | 435212 | Aseni | 479 | 474 | 99 | Work In Progress | Not Certified |
| 2 | Barabanki | Banki | Gokul Pur | 435216 | Gokul Pur | 393 | 390 | 99 | Work In Progress | Not Certified |