Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | PNC-SPML-JV | 20077073 | Tamarsepur & Paradeepu Water Supply Scheme | 356.83 | 177.37 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 14594.00 | 13698.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Harakh | Para Depu | 435337 | Paradeepu | 268 | 264 | 99 | Work In Progress | Not Certified |
| 2 | Barabanki | Harakh | Para Depu | 435338 | Rasool Pur | 171 | 167 | 98 | Work In Progress | Not Certified |
| 3 | Barabanki | Harakh | Tamarsepur | 435339 | Tamrase Pur | 221 | 218 | 99 | Work In Progress | Not Certified |
| 4 | Barabanki | Harakh | Tamarsepur | 435340 | Tahee Pur | 135 | 132 | 98 | Work In Progress | Not Certified |