Scheme Details
DISTRICT Barabanki
AGENCY PNC-SPML-JV
SCHEME ID 20077089
SCHEME NAME Baraiya Water Supply Scheme
ESTIMATED COST 265.27
EXPENDITURE 178.98
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 63
Procured 63 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 11468.00 Meter
Length Laid 11468.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Suratganj Baraiya 434826 Baraiya 506 499 99% Work In Progress Not Certified
2 Barabanki Suratganj Baraiya 434827 Ainuddin Pur 200 199 100% Work In Progress Not Certified