DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20077304
SCHEME NAME
SURAHI BUJURG WATER SUPPLY SCHEME
ESTIMATED COST
353.72
EXPENDITURE
212.41
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
10838.00
Meter
Length Laid
10838.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Mirzapur | SURAHI BUJURG | 463459 | Surahi Bujurg | 357 | 332 | 93% | Work In Progress | Not Certified |
| 2 | Azamgarh | Mirzapur | SURAHI BUJURG | 463460 | Ram Raj Pur | 107 | 98 | 92% | Work In Progress | Not Certified |
| 3 | Azamgarh | Mirzapur | SURAHI BUJURG | 680476 | Chak Maah | 6 | 1 | 17% | Work In Progress | Not Certified |