Scheme Details
DISTRICT
Azamgarh
AGENCY
M/s Sudhakara Infratech Pvt. Ltd
SCHEME ID
20077346
SCHEME NAME
JAMIN MANJHARIYA & PIPAROPUR WATER SUPPLY SCHEME
ESTIMATED COST
426.32
EXPENDITURE
277.84
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18535.00
Meter
Length Laid
13795.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Azamgarh | Sathiyaon | Piparopur | 463057 | Piparopur | 246 | 240 | 98% | Work In Progress | Not Certified |
| 2 | Azamgarh | Sathiyaon | Jamin Manjhriya | 463058 | Dhakawa | 290 | 285 | 98% | Work In Progress | Not Certified |
| 3 | Azamgarh | Sathiyaon | Jamin Manjhriya | 463059 | Manjhriya | 61 | 57 | 93% | Work In Progress | Not Certified |
| 4 | Azamgarh | Sathiyaon | Jamin Manjhriya | 463060 | Asmarpur | 1 | 1 | 100% | Har Ghar Jal | Not Certified |
| 5 | Azamgarh | Sathiyaon | Jamin Manjhriya | 463061 | Jamin Manjhriya | 78 | 75 | 96% | Work In Progress | Not Certified |