Scheme Details
S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Approve By Agency Status | Approve By EE Status | Automation Status |
---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Dehat | VSA | 20077475 | selhupur & salarpur &musarai | 480.22 | 294.23 | Verified | Verified | Not Integrated |
Scheme Assigne Villages
Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | Handed Over Villages |
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Kanpur Dehat | Amrodha | Selhupur | 421618 | Madanupur | 100 | 100 | 100 | Har Gar Jal | Not Certified | Not Verified |
2 | Kanpur Dehat | Amrodha | Selhupur | 421619 | Selhupur | 255 | 252 | 99 | Work In Progress | Not Certified | Not Verified |
3 | Kanpur Dehat | Amrodha | Musanagar Bangar | 421620 | Musanagar Bangar | 424 | 424 | 100 | Har Gar Jal | Certified | Verified |
4 | Kanpur Dehat | Amrodha | Salarpur | 651786 | Nagwan Baangar | 75 | 74 | 99 | Work In Progress | Not Certified | Not Verified |
5 | Kanpur Dehat | Amrodha | Salarpur | 659627 | Salarpur | 130 | 130 | 100 | Har Gar Jal | Not Certified | Not Verified |
Scheme Progress
Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
5 | 2 | 2 | 2 | 2 | 1 | 1 | 0 | 58 | 58 | Yes | 0 | NA | No | 18081.00 | 18081.00 |