Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Balrampur
AGENCY Dara- Eco Protection (JV)
SCHEME ID 20077524
SCHEME NAME MANPUR SONBARSA & DHAWAI GRAM PANCHAYAT WATER SUPPLY
ESTIMATED COST 366.61
EXPENDITURE 5.15
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15203.00 Meter
Length Laid 14500.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Balrampur Pachperwa Manpur Sonbarsa 444104 Manpur 275 253 92% Work In Progress Not Certified
2 Balrampur Pachperwa Dhawai 444109 Dhawai 363 320 88% Work In Progress Not Certified