Scheme Details
DISTRICT
Moradabad
AGENCY
NKG-PRIMUS (JV)
SCHEME ID
20077717
SCHEME NAME
Fatehpur Bisnoi and Niamatulahnagar Urf Mithanpur GP WSS
ESTIMATED COST
508.61
EXPENDITURE
262.66
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17546.00
Meter
Length Laid
17730.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Chhajlet | Naimtullahnagar Urf Mithanpur | 388073 | Uchaiti | 20 | 19 | 95% | Work In Progress | Not Certified |
| 2 | Moradabad | Chhajlet | Naimtullahnagar Urf Mithanpur | 388074 | Naimtullahnagar Urf Mithanpur | 307 | 301 | 98% | Work In Progress | Not Certified |
| 3 | Moradabad | Chhajlet | Fatehpur Bisnoi | 388075 | Fatehpur Bisnoi | 735 | 728 | 99% | Work In Progress | Not Certified |