Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Chandauli
AGENCY GA INFRA - BABA (JV)
SCHEME ID 20077806
SCHEME NAME MISHRAPUR_KOHARA WS
ESTIMATED COST 428.25
EXPENDITURE 208.58
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 7
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 27
Procured 27 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 19960.00 Meter
Length Laid 15854.00 Meter

Scheme Assigned Villages

7 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Chandauli Dhanapur Kohara 474345 Kohara 236 186 79% Work In Progress Not Certified
2 Chandauli Dhanapur Mishrapur 474349 Pura Jagarnath Mishra 19 19 100% Har Ghar Jal Not Certified
3 Chandauli Dhanapur Mishrapur 474350 Puracheta Dube 98 91 93% Work In Progress Not Certified
4 Chandauli Dhanapur Mishrapur 474351 Mishrapura 18 18 100% Har Ghar Jal Not Certified
5 Chandauli Dhanapur Mishrapur 474352 Barauda Bamhnauli 118 110 93% Work In Progress Not Certified
6 Chandauli Dhanapur Mishrapur 474353 Baruada Khalsa 7 7 100% Har Ghar Jal Not Certified
7 Chandauli Dhanapur Mishrapur 658468 Puraseeta Mishra 4 4 100% Har Ghar Jal Not Certified