Scheme Details
DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20078168
SCHEME NAME
Saidpur chunnilal Water Supply Scheme
ESTIMATED COST
273.40
EXPENDITURE
130.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
27
Procured
27
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
7935.00
Meter
Length Laid
7920.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Bithiri Chainpur | Saidpur Chunni Lal | 403787 | Saidpur Chunni Lal | 549 | 541 | 99% | Work In Progress | Not Certified |