Scheme Details
DISTRICT
Sultanpur
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20078202
SCHEME NAME
DHESARUA & MEERRDASPUR WSS
ESTIMATED COST
673.35
EXPENDITURE
322.79
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
43
Procured
43
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
36268.00
Meter
Length Laid
36543.00
Meter
Scheme Assigned Villages
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Kurebhar | Dhesarua | 440145 | Dhesarua | 642 | 624 | 97% | Work In Progress | Not Certified |
| 2 | Sultanpur | Kurebhar | Meerdaspur | 440148 | Churkuna Asharafpur | 102 | 96 | 94% | Work In Progress | Not Certified |
| 3 | Sultanpur | Kurebhar | Meerdaspur | 440149 | Mirdaspur | 155 | 146 | 94% | Work In Progress | Not Certified |