Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20078349 | PAIKAULI GOGP | 667.38 | 323.37 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 51 | 51 | Yes | 0 | NA | No | 30699.00 | 30699.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Sukrauli | Awarawa | 458324 | Awarawa | 283 | 269 | 95 | Work In Progress | Not Certified | 
| 2 | Kushi Nagar | Sukrauli | Awarawa | 458325 | Barwa | 91 | 91 | 100 | Har Gar Jal | Not Certified | 
| 3 | Kushi Nagar | Sukrauli | Paikauli | 458352 | Paikauli | 414 | 390 | 94 | Work In Progress | Not Certified | 
| 4 | Kushi Nagar | Sukrauli | Jagdishpur | 458354 | Jagdishpur | 378 | 357 | 94 | Work In Progress | Not Certified | 
| 5 | Kushi Nagar | Sukrauli | Paikauli | 458458 | PAIKAULI | 281 | 0 | 0 | Work In Progress | Not Certified |