Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20078370 | BARMALPUR & HATWA VILLAGE WATER SUPPLY SCHEME | 372.76 | 141.08 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 23 | 0 | NA | 0 | NA | No | 19746.00 | 18000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dobhi | Hatwa | 471397 | Parsupur | 58 | 55 | 95 | Work In Progress | Not Certified |
| 2 | Jaunpur | Dobhi | Hatwa | 471398 | Hatwa | 183 | 183 | 100 | Har Gar Jal | Not Certified |
| 3 | Jaunpur | Dobhi | Barmalpur | 471399 | Barmalpur | 221 | 216 | 98 | Work In Progress | Not Certified |