Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Meerut | Power Mech Projects Ltd | 20078412 | GOVINDPUR SAKARPUR & NAWAL SURAJPUR | 480.73 | 335.62 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 37 | 37 | Yes | 0 | NA | No | 15219.00 | 13784.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Meerut | Parikshitgarh | Nawal Surajpur | 391619 | Nawal Surajpur | 389 | 371 | 95 | Work In Progress | Not Certified | 
| 2 | Meerut | Machhara | Govindpur Sakarpur | 391677 | Govindpur Sakarpur | 527 | 519 | 98 | Work In Progress | Not Certified |