Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Meerut | Power Mech Projects Ltd | 20078419 | MUBARIKPUR, PACHGAONPATTI & SANWAL | 494.88 | 364.12 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 44 | 44 | Yes | 0 | NA | No | 15682.00 | 16950.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Meerut | Machhara | Mubarikpur | 391641 | Mubarikpur | 447 | 434 | 97 | Work In Progress | Not Certified |
| 2 | Meerut | Machhara | Mubarikpur | 391642 | Barauda | 32 | 1 | 3 | Work In Progress | Not Certified |
| 3 | Meerut | Rajpura | Pachgaon Patti Sanwal | 391847 | Pachgaon Patti Sanwal | 339 | 338 | 100 | Work In Progress | Not Certified |