Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20078513 | DHOLAHA GROUP OF G.P.s | 482.65 | 265.67 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 37 | 37 | Yes | 0 | NA | No | 15560.00 | 12446.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Nebua Naurangiya | Dholha | 457606 | Dholha | 562 | 493 | 88 | Work In Progress | Not Certified | 
| 2 | Kushi Nagar | Nebua Naurangiya | Parsu Rampur | 457623 | Harpur Tappa Batesara 46 | 236 | 236 | 100 | Har Gar Jal | Certified |