Scheme Details
DISTRICT Sitapur
AGENCY NCC Ltd.
SCHEME ID 20078530
SCHEME NAME Mirpur & Newada Water Supply Scheme
ESTIMATED COST 357.29
EXPENDITURE 197.12
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 25
Procured 25 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14520.00 Meter
Length Laid 14520.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Sitapur Khairabad Mirpur 410607 Nerpur 449 449 100% Har Ghar Jal Not Certified
2 Sitapur Khairabad Newada Barua 410608 Newada Barua 188 188 100% Har Ghar Jal Not Certified