Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | NCC Ltd. | 20078560 | PAKARI GOGP | 615.37 | 319.53 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 44 | 44 | Yes | 0 | NA | No | 21500.00 | 21500.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Kushi Nagar | Kaptanganj | Pakari | 458031 | Sugga Pakar | 34 | 34 | 100 | Har Gar Jal | Not Certified |
| 2 | Kushi Nagar | Kaptanganj | Pakari | 458033 | Pakari | 281 | 281 | 100 | Har Gar Jal | Not Certified |
| 3 | Kushi Nagar | Kaptanganj | Mujdiha | 458068 | Mujdiha | 320 | 240 | 75 | Work In Progress | Not Certified |
| 4 | Kushi Nagar | Kaptanganj | Lakhima | 458077 | Lakhima | 390 | 384 | 98 | Work In Progress | Not Certified |