S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Kanpur Nagar VSA 20078714 Kunwarpur & Newada seini 346.52 96.14 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 1 35 35 Yes 0 NA No 12840.00 6952.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Kanpur Nagar Bilhaur Newada Shah 422018 Newada Shah 185 183 99 Work In Progress Not Certified
2 Kanpur Nagar Bilhaur Newada Shah 422019 Newada Saina 79 78 99 Work In Progress Not Certified
3 Kanpur Nagar Shivrajpur Kunwarpur 422085 Kunwarpur 190 190 100 Har Gar Jal Not Certified
4 Kanpur Nagar Shivrajpur Kunwarpur 422086 Rawalalpur 160 160 100 Har Gar Jal Not Certified