1 Sultanpur Vindhya-GAJA (JV) 20078785 BAINI & PARSIPUR & SARAIYA WSS 541.52 265.13 Verified Verified Not Integrated

Scheme Assigne Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified Handed Over Villages
1 Sultanpur Lambhua Saraiya 440874 Pandeypur 80 78 98 Work In Progress Not Certified Not Verified
2 Sultanpur Lambhua Baini 440875 Baini 220 214 97 Work In Progress Not Certified Not Verified
3 Sultanpur Lambhua Saraiya 440876 Saraiya 139 134 96 Work In Progress Not Certified Not Verified
4 Sultanpur Lambhua PARSIPUR 440878 BIKAHAR 38 22 58 Work In Progress Not Certified Not Verified
5 Sultanpur Lambhua PARSIPUR 440879 Parsipur 97 91 94 Work In Progress Not Certified Not Verified
6 Sultanpur Lambhua PARSIPUR 440880 Hirawanpur 90 74 82 Work In Progress Not Certified Not Verified
7 Sultanpur Lambhua PARSIPUR 440881 PARMANPUR 34 25 74 Work In Progress Not Certified Not Verified
8 Sultanpur Lambhua PARSIPUR 440882 Antapur 36 29 81 Work In Progress Not Certified Not Verified

Scheme Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
8 2 2 2 2 1 0 0 32 32 Yes 0 NA No 32820.00 32820.00