Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Fatehpur Power Mech Projects Ltd 20078862 Chaimalpur 225.00 68.17 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
3 1 1 1 1 1 1 0 18 18 Yes 0 NA No 9641.00 9892.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Fatehpur Hathgaon Chaimalpur 428269 Chaimalpur 98 93 95 Work In Progress Not Certified
2 Fatehpur Hathgaon Chaimalpur 428270 Mustafapur 69 43 62 Work In Progress Not Certified
3 Fatehpur Hathgaon Chaimalpur 428271 Iradatpur Dhami 141 7 5 Work In Progress Not Certified