Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Power Mech Projects Ltd | 20078862 | Chaimalpur | 225.00 | 68.17 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 18 | 18 | Yes | 0 | NA | No | 9641.00 | 9892.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Fatehpur | Hathgaon | Chaimalpur | 428269 | Chaimalpur | 98 | 93 | 95 | Work In Progress | Not Certified |
| 2 | Fatehpur | Hathgaon | Chaimalpur | 428270 | Mustafapur | 69 | 43 | 62 | Work In Progress | Not Certified |
| 3 | Fatehpur | Hathgaon | Chaimalpur | 428271 | Iradatpur Dhami | 141 | 7 | 5 | Work In Progress | Not Certified |