Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | NCC Ltd. | 20078932 | GADANPUR + SHANKARPUR + TIMRAKH GRAM PANCHAYAT WATER SUPPLY SCHEME | 545.37 | 277.13 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 8 | 8 | Yes | 0 | NA | No | 35855.00 | 38000.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mainpuri | Karhal | Shankarpur | 400315 | Shankarpur | 199 | 195 | 98 | Work In Progress | Not Certified |
| 2 | Mainpuri | Karhal | Shankarpur | 400316 | Nasirpur | 114 | 112 | 98 | Work In Progress | Not Certified |
| 3 | Mainpuri | Karhal | Timrakh | 400392 | Timrakh | 289 | 289 | 100 | Har Gar Jal | Not Certified |
| 4 | Mainpuri | Karhal | Gadanpur | 400397 | Gadanpur | 346 | 343 | 99 | Work In Progress | Not Certified |